The Science Campus, Bordeaux

Bordeaux
2017

Campus Bordeaux Ronald Sirio Architectes Facade

Redevelopment of 11 existing university buildings, including six “air gap” structures based on bioclimatic double-envelope glazing technology, and the construction of five new buildings.

Bordeaux University History
Bordeaux University Conservative Dissipative Systems
Bordeaux University Summer Winter Cross-Section
  1. In winter: T°C in the bioclimatic facade = 4°C in the north and 7 °C in the south on average over the heating period compared to the outside T°C. Thermal losses of the envelope divided by 3.
  2. In summer: the air speed in the bioclimatic facade equals 1 m/s, promoting heat dissipation

Driven by the desire to give a “new life cycle” to these buildings, from a technical, functional, and social perspective, the main goal was to preserve their intrinsic qualities while harnessing their strengths and eliminating any weaknesses. This optimization approach to the existing structures dovetailed with the national goal to increase the energy retrofitting of existing buildings, and university buildings especially, via the “Campus Plan”.

To enhance the architectural aspect of eight historic buildings, the team developed an innovative solution, lining the facades with a glass envelope as opposed to insulating them from the outside, to preserve their existing qualities. In winter, the double envelope creates a cushion of warm air around the building thereby insulating the interior spaces; in summer, the double envelope fitted with mobile grilles creates a thermo-siphon effect and natural ventilation all around the building, cooling the interior spaces. This solution reduced energy requirements while increasing comfort for users, the glass envelope proving to be multipurpose, for example as a surface for signage and video mapping.

The work was carried out in several phases to avoid interruption to campus activities.

Bordeaux University Air Flow Studies
  • Client

    Université de Bordeaux – SRIA

  • Team

    Paul Chemetov, Debarre-Duplantier Asociés and Ronald Sirio, DV Construction, Quille Construction, ECCTA Ingénierie (structure and fluids), TERRELL SAS (facades), EXPRIMM (maintenance)

  • Performance

    Bioclimatic facades

  • Label

    HQE - BREEAM very good - BBC renovation

  • Surface

    85,000 m² including 53,000 m² NFA (rehabilitated) and 32,000 m² NFA (new)

  • Cost

    €122M

  • Schedule

    2011 – Delivered in 2017

  • Photographs

    11h45

  • AFB Team

    AFB alumni: Lucas Dugrenot, Yohan Gauchet, Simon Guesdon, François-Xavier Parent, and Rémi Ségales